Nabucco Paves the Way for Construction
The value of the entire package of long lead items needed for the pipeline construction is around EUR 3.5 bn
AUTHOR: publics.bg


  • © Nabucco Gas Pipeline

This week Nabucco Gas Pipeline International launched the pre-qualification process as a starting phase for the procurement of long lead items needed for the pipeline construction. The value of the entire package is around EUR 3.5 bn. and the deadline for companies to participate in the prequalification is 17th May. This was announced by the company in an official press release. “Long lead items - like pipes and valves - are the cornerstone for pipeline construction, and account for a considerable part of the overall investment costs. The prequalification process will identify the most eligible companies and is the basis for a successful procurement proc-ess,” Nabucco Managing Director Reinhard Mitschek stated.

The prequalification process will provide the Nabucco consortium with the opportunity to thoroughly assess the supplier market on a worldwide basis. Interest by potential suppliers has been extensive from the outset. After the prequalification process is completed, Nabucco intends to launch the respective tender. “The prequalification for long lead items is a substantial step towards starting construction at the end of 2011”, said Mitschek.

The long lead items required in this package include line pipes, valves and bends, which need to be ordered in advance to meet the construction schedule. The materials specifica-tion has been prepared by engineering companies in accordance with internationally rec-ognized standards, and the technical prequalification process of the respective procure-ment is to be preformed by an independent third party. On another note, the selection of the route corridor has been recently completed for the first phase of the project and the right of way and permission process for the environmental and social assessment and construction permit in the Nabucco countries is currently in progress.

The Nabucco gas pipeline will run for over 3,300 km from Turkey via Bulgaria, Romania and Hungary to Vienna, close to the Baumgarten gas hub. Currently, the pipeline shareholders include OMV Gas&Power, MOL, Transgaz, Bulgarian Energy Holding, BOTAS and RWE. The planned capacity for the final development stage is 31 billion cubic meter. The total capital investments based on the project assessments of summer 2008 was EUR 7.9 billion. Construction will start 2011, first gas will flow 2014.


TAGS: Nabucco | gas | pipeline | construction | preparation 


All world news

No published comments
Login to comment


Interview

20.03.2022  Teodor Bobochikov, Managing Partner, V-Ridium
Energy Transformation – Trends and drivers
Full text

Events

No records in this category!

Poll

What kind of transport do you use to get to work?











 



We use cookies to ensure we give you the best browsing experience on our website. Find out more on how we use cookies and how you can change your settings.

Cookies

What are cookies ?

A cookie is a small text file that a website saves on your computer or mobile device when you visit the site. Cookies are widely used in order to make websites work, or work more efficiently, as well as to provide information to the owners of the site.

How do we use cookies?

Website use Google Analytics, a web analytics service provided by Google, Inc. ("Google") to help analyse the use of this website. For this purpose, Google Analytics uses"cookies", which are text files placed on your computer.

The information generated by the cookies about your use of this website - standard internet log information (including your IP address) and visitor behaviour information in an anonymous form - will be transmitted to and stored by Google including on servers in the United States. Google will anonymize the information sent by removing the last octet of your IP address prior to its storage.

According to Google Analytics terms of service, Google will use this information for the purpose of evaluating your use of the website and compiling reports on website activity.

We not use, and not allow any third party to use the statistical analytics tool to track or to collect any personally identifiable information of visitors to this site. Google may transfer the information collected by Google Analytics to third parties where required to do so by law, or where such third parties process the information on Google`s behalf.

According to Google Analytics terms of service, Google will not associate your IP address with any other data held by Google.

You may refuse the use of Google Analytics cookies by downloading and installing Google Analytics Opt-out Browser Add-on. The add-on communicates with the Google Analytics JavaScript (ga.js) to indicate that information about the website visit should not be sent to Google Analytics.

Cookies are also used to record if you have agreed (or not) to our use of cookies on this site, so that you are not asked the question every time you visit the site.

Google Analytics Opt-out Browser Add-on

How to control cookies?

You can control and/or delete cookies as you wish. You can delete all cookies that are already on your computer and you can set most browsers to prevent them from being placed.

All about cookies

Managing cookies in your browser

Most browsers allow you to:
  • see what cookies you have got and delete them on an individual basis
  • block third party cookies
  • block cookies from particular sites
  • block all cookies from being set
  • delete all cookies when you close your browser

If you chose to delete cookies, you should be aware that any preferences will be lost. Also, if you block cookies completely many websites (including ours) will not work properly and webcasts will not work at all. For these reasons, we do not recommend turning cookies off when using our webcasting services.
X
} catch(err) {}